Action Date | Action Description |
---|---|
Engineering Report | |
Jan 02, 2024 | Assent Application Received |
Jan 05, 2024 | Administrative Review for Completeness |
Jan 30, 2024 | Eng Team Review for Completeness |
Jan 30, 2024 | Deficient Application - Owner Notification Sent |
Aug 28, 2024 | Deficiency Response Received |
Sep 04, 2024 | Eng Team Review for Completeness |
Sep 04, 2024 | Application Accepted |
Sep 04, 2024 | Project Manager |
Sep 19, 2024 | HPHC Historical Preservation No Effect |