Action Date | Action Description |
---|---|
Jun 15, 2011 | Assent Application Received |
Jun 15, 2011 | Administrative Review for Completeness |
Aug 03, 2011 | Team Review for Completeness |
Aug 03, 2011 | Team Review for Completeness |
Aug 03, 2011 | Application Accepted |
Aug 24, 2011 | Additional Information Received |
Sep 06, 2011 | 30 day Public Notice Issued |
Sep 09, 2011 | HPHC Historical Preservation No Effect |
Oct 06, 2011 | Public Notice End Date |
Dec 22, 2011 | Engineering Report |
Dec 29, 2011 | Biologist Report |
Jan 03, 2012 | Typist for Processing |
Jan 03, 2012 | Executive Sign Off |
Jan 03, 2012 | Sent to Photo Copy |
Jan 03, 2012 | Permit Approved |
Jan 17, 2012 | Land Evidence Date |
Jan 23, 2012 | US Army Corps of Engineers Approval Received |
Mar 28, 2012 | Water Quality Certification |
Dec 11, 2012 | Commencement of Work Notice received |