Action Date | Action Description |
---|---|
Jun 28, 2011 | Assent Application Received |
Jun 28, 2011 | Administrative Review for Completeness |
Jul 07, 2011 | Team Review for Completeness |
Jul 07, 2011 | Team Review for Completeness |
Jul 07, 2011 | Plans Received |
Jul 07, 2011 | Application Accepted |
Aug 19, 2011 | Biologist Report |
Aug 19, 2011 | Engineering Report |
Aug 22, 2011 | Plans Received |
Aug 22, 2011 | Plans Received |
Aug 24, 2011 | Permit Approved |
Aug 24, 2011 | Typist for Processing |
Aug 25, 2011 | Executive Sign Off |
Aug 25, 2011 | Sent to Photo Copy |
Sep 02, 2011 | Land Evidence Date |
Sep 20, 2011 | HPHC Historical Preservation No Effect |