Action Date | Action Description |
---|---|
Jul 11, 2011 | Maintenance Certification Request |
Jul 12, 2011 | Administrative Review for Completeness |
Jul 12, 2011 | Team Review for Completeness |
Jul 12, 2011 | Team Review for Completeness |
Jul 12, 2011 | Application Accepted |
Jul 25, 2011 | Biologist Report |
Jul 25, 2011 | Engineering Report |
Jul 27, 2011 | Typist for Processing |
Jul 27, 2011 | Permit Approved |
Aug 01, 2011 | Executive Sign Off |
Aug 01, 2011 | Sent to Photo Copy |
Sep 13, 2011 | HPHC Historical Preservation No Effect |