Action Date | Action Description |
---|---|
Jul 29, 2011 | Assent Application Received |
Aug 01, 2011 | Administrative Review for Completeness |
Aug 11, 2011 | Team Review for Completeness |
Aug 11, 2011 | Team Review for Completeness |
Aug 11, 2011 | Application Accepted |
Aug 11, 2011 | Category A* (Docks) |
Aug 15, 2011 | Objections/Comments Received |
Aug 16, 2011 | 30 day Public Notice Issued |
Sep 07, 2011 | HPHC Historical Preservation No Effect |
Sep 15, 2011 | Mail Agenda Notice |
Sep 16, 2011 | Public Notice End Date |
Sep 27, 2011 | Council Approval Granted |
Sep 27, 2011 | Semi-Monthly Meeting Held |
Sep 27, 2011 | Semi-Monthly Meeting Date Scheduled |
Sep 30, 2011 | Stipulation Package from Biologist |
Sep 30, 2011 | Stipulation Package by Engineer |
Sep 30, 2011 | Biologist Report |
Sep 30, 2011 | Engineering Report |
Oct 03, 2011 | Typist for Processing |
Oct 05, 2011 | Legal Response/Decision |
Oct 06, 2011 | US Army Corps of Engineers Approval Received |
Oct 13, 2011 | Executive Sign Off |
Oct 13, 2011 | Sent to Photo Copy |
Oct 13, 2011 | Permit Approved |
Jan 27, 2012 | Land Evidence Date |