Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jul 28, 2016 | Assent Application Received |
Jul 29, 2016 | Administrative Review for Completeness |
Aug 10, 2016 | Team Review for Completeness |
Aug 10, 2016 | Deficient Application - Owner Notification Sent |
Aug 23, 2016 | Deficient Application Picked Up |
Oct 31, 2016 | Deficiency Response Received |
Nov 01, 2016 | Team Review for Completeness |
Nov 02, 2016 | Application Accepted |
Nov 02, 2016 | Category A* (Docks) |
Nov 02, 2016 | Team Review for Completeness |
Nov 10, 2016 | HPHC Historical Preservation No Effect |
Nov 30, 2016 | 30 day Public Notice Issued |
Dec 30, 2016 | Public Notice End Date |
Jan 23, 2017 | US Army Corps of Engineers Approval Received |
Jan 24, 2017 | Typist for Processing |
Jan 24, 2017 | Sent to Photo Copy |
Jan 24, 2017 | Permit Approved |
Jan 24, 2017 | Biologist Report |
Mar 22, 2017 | Land Evidence Date |