Action Date | Action Description |
---|---|
Aug 23, 2016 | Assent Application Received |
Aug 23, 2016 | Administrative Review for Completeness |
Aug 29, 2016 | Team Review for Completeness |
Aug 29, 2016 | Application Accepted |
Sep 21, 2016 | 30 day Public Notice Issued |
Oct 05, 2016 | HPHC Historical Preservation No Effect |
Oct 21, 2016 | Public Notice End Date |
Oct 28, 2016 | Special Exception Public Hearing Notice mailed |
Nov 16, 2016 | Engineering Report |
Nov 21, 2016 | Mail Agenda Notice |
Nov 22, 2016 | Semi-Monthly Meeting Postponed |
Nov 22, 2016 | Semi-Monthly Meeting Date Scheduled |
Nov 29, 2016 | Semi-Monthly Meeting Date Scheduled |
Nov 29, 2016 | Council Approval Granted |
Dec 01, 2016 | Legal Response/Decision |
Dec 08, 2016 | Additional Information Received |
Dec 14, 2016 | Stipulation Package by Engineer |
Jan 04, 2017 | Typist for Processing |
Jan 04, 2017 | Executive Sign Off |
Jan 04, 2017 | Sent to Photo Copy |
Jan 04, 2017 | Permit Approved |