Action Date | Action Description |
---|---|
Aug 30, 2016 | Assent Application Received |
Aug 30, 2016 | Application Accepted |
Aug 31, 2016 | Administrative Review for Completeness |
Sep 01, 2016 | Team Review for Completeness |
Sep 01, 2016 | Team Review for Completeness |
Oct 05, 2016 | Plans Received |
Oct 13, 2016 | Biologist Report |
Oct 13, 2016 | Engineering Report |
Oct 14, 2016 | Typist for Processing |
Oct 17, 2016 | Plans Received |
Oct 18, 2016 | Executive Sign Off |
Oct 18, 2016 | Sent to Photo Copy |
Oct 18, 2016 | Permit Approved |