Action Date | Action Description |
---|---|
Sep 01, 2016 | Assent Application Received |
Sep 02, 2016 | Administrative Review for Completeness |
Sep 02, 2016 | Team Review for Completeness |
Sep 02, 2016 | Application Accepted |
Sep 14, 2016 | Plans Received |
Sep 29, 2016 | Biologist Report |
Oct 03, 2016 | Typist for Processing |
Oct 04, 2016 | Executive Sign Off |
Oct 04, 2016 | Sent to Photo Copy |
Oct 04, 2016 | Permit Approved |
Oct 18, 2016 | Land Evidence Date |