Action Date | Action Description |
---|---|
Sep 08, 2016 | Administrative Review for Completeness |
Sep 08, 2016 | Assent Application Received |
Sep 12, 2016 | Category B assigned |
Sep 12, 2016 | Application Accepted |
Sep 12, 2016 | Team Review for Completeness |
Sep 12, 2016 | Team Review for Completeness |
Sep 30, 2016 | Plans Received |
Oct 03, 2016 | Additional Information Received |
Oct 04, 2016 | 30 day Public Notice Issued |
Oct 14, 2016 | HPHC Historical Preservation No Effect |
Nov 03, 2016 | Objections/Comments Received |
Nov 04, 2016 | Public Notice End Date |
Nov 15, 2016 | Biologist Report |
Nov 15, 2016 | Plans Received |
Nov 15, 2016 | Stipulation Package from Biologist |
Nov 23, 2016 | Special Exception Public Hearing Notice mailed |
Dec 07, 2016 | Plans Received |
Dec 07, 2016 | Engineering Report |
Dec 07, 2016 | Stipulation Package by Engineer |
Dec 13, 2016 | Semi-Monthly Meeting Date Scheduled |
Dec 13, 2016 | Council Approval Granted |
Dec 15, 2016 | Stipulation Package from Biologist |
Dec 15, 2016 | Stipulation Package by Engineer |
Dec 28, 2016 | Council Approval Granted |
Jan 03, 2017 | 30 Day Appeal Notification to Owner |
Jan 03, 2017 | Legal Response/Decision |
Mar 06, 2017 | Permit Approved |
Mar 10, 2017 | Land Evidence Date |