Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jun 28, 2022 | Assent Application Received |
Jun 30, 2022 | Administrative Review for Completeness |
Jul 13, 2022 | Bio Team Review for Completeness |
Jul 13, 2022 | Application Accepted |
Jul 15, 2022 | Project Manager |
Jul 15, 2022 | Category A* (Docks) |
Aug 15, 2022 | HPHC Historical Preservation No Effect |
Aug 23, 2022 | Plans Received |
Sep 15, 2022 | Correspondence Received |
Oct 05, 2022 | Engineering Report |
Oct 31, 2022 | Public Notice End Date Extension Granted |
Nov 14, 2022 | Comments Received |
Nov 22, 2022 | Biologist Report |
Nov 29, 2022 | Typist for Processing |
Nov 29, 2022 | Executive Sign Off |
Nov 29, 2022 | Sent to Photo Copy |
Nov 29, 2022 | Permit Approved |
Dec 01, 2022 | Permit Mailed |
Dec 16, 2022 | Land Evidence Date |