Action Date | Action Description |
---|---|
Sep 17, 1994 | Application Accepted |
Sep 30, 1994 | Engineering Report |
Nov 16, 1994 | Permit Approved |
Nov 29, 1994 | Land Evidence Date |
Mar 19, 2001 | Modification Request |
Jun 11, 2001 | 30 day Public Notice Issued |
Jul 27, 2001 | Dock sub-committee Approved |
Jul 27, 2001 | Engineering Report |
Jul 30, 2001 | Modification Approved |
Aug 20, 2001 | Land Evidence Date |
Jul 27, 2002 | Biologist Report |
May 03, 2007 | Modification Request |
May 07, 2007 | Administrative Review for Completeness |
May 09, 2007 | Team Review for Completeness |
May 09, 2007 | Team Review for Completeness |
May 17, 2007 | HPHC Historical Preservation No Effect |
Jul 02, 2007 | Plans Received |
Jul 16, 2007 | 30 day Public Notice Issued |
Aug 16, 2007 | Public Notice End Date |
Sep 13, 2007 | Dock Meeting -- Approval |
Oct 02, 2007 | Biologist Report |
Oct 02, 2007 | Engineering Report |
Oct 03, 2007 | Typist for Processing |
Oct 03, 2007 | Executive Sign Off |
Oct 03, 2007 | Sent to Photo Copy |
Oct 03, 2007 | Modification Approved |
Oct 03, 2007 | US Army Corp of Engineers Permit Date |
Oct 05, 2007 | US Army Corps of Engineers Approval Received |
Nov 07, 2007 | Land Evidence Date |
Jun 20, 2012 | Extension Toll letter mailed |