Action Date | Action Description |
---|---|
Sep 17, 1994 | Application Accepted |
Nov 28, 1994 | Engineering Report |
Nov 28, 1994 | Permit Approved |
Nov 28, 1994 | Land Evidence Date |
Dec 02, 2008 | Modification Request |
Dec 05, 2008 | Administrative Review for Completeness |
Dec 08, 2008 | Team Review for Completeness |
Dec 08, 2008 | Team Review for Completeness |
Dec 08, 2008 | Deficient Application - Owner Notification Sent |
Dec 11, 2008 | Deficient Application Picked Up |
Feb 19, 2009 | Deficiency Response Received |
Feb 19, 2009 | Administrative Review for Completeness |
Feb 19, 2009 | Team Review for Completeness |
Feb 19, 2009 | Team Review for Completeness |
Feb 19, 2009 | Deficient Application - Owner Notification Sent |
Feb 24, 2009 | Deficient Application Picked Up |
Feb 27, 2009 | Deficiency Response Received |
Feb 27, 2009 | Administrative Review for Completeness |
Mar 06, 2009 | Team Review for Completeness |
Mar 06, 2009 | Team Review for Completeness |
Mar 06, 2009 | Deficient Application - Owner Notification Sent |
Apr 03, 2009 | Deficiency Response Received |
Apr 06, 2009 | Administrative Review for Completeness |
Apr 07, 2009 | Team Review for Completeness |
Apr 07, 2009 | Team Review for Completeness |
Apr 16, 2009 | 30 day Public Notice Issued |
Apr 21, 2009 | HPHC Historical Preservation No Effect |
Apr 23, 2009 | Correspondence Received |
Apr 23, 2009 | Correspondence Received |
Jun 11, 2009 | Correspondence Received |
Jun 12, 2009 | Public Notice End Date |
Jun 26, 2009 | Dock Meeting Scheduled (Admin) |
Aug 04, 2009 | Plans Received |
Aug 04, 2009 | 30 day Public Notice Issued |
Sep 16, 2009 | Correspondence Received |
Sep 18, 2009 | Public Notice End Date |
Oct 14, 2009 | Modification Approved |
Oct 14, 2009 | Biologist Report |
Oct 14, 2009 | Engineering Report |
Oct 26, 2009 | Land Evidence Date |