Action Date | Action Description |
---|---|
May 30, 1995 | Application Accepted |
Jun 27, 1995 | Engineering Report |
Jun 28, 1995 | Permit Approved |
Jun 28, 1995 | Land Evidence Date |
Mar 06, 2017 | Modification Request |
Mar 07, 2017 | Administrative Review for Completeness |
Mar 08, 2017 | Team Review for Completeness |
Mar 08, 2017 | Application Accepted |
Mar 20, 2017 | HPHC Historical Preservation No Effect |
Mar 21, 2017 | 30 day Public Notice Issued |
Apr 20, 2017 | US Army Corps of Engineers Approval Received |
Apr 21, 2017 | Public Notice End Date |
Jul 13, 2017 | Plans Received |
Jul 19, 2017 | Dock Meeting -- Approval |
Jul 20, 2017 | Typist for Processing |
Jul 20, 2017 | Executive Sign Off |
Jul 20, 2017 | Sent to Photo Copy |
Jul 20, 2017 | Modification Approved |
Jul 20, 2017 | Biologist Report |
Aug 15, 2017 | Land Evidence Date |