Action Date | Action Description |
---|---|
Jun 19, 1995 | Application Accepted |
Jul 20, 1995 | Biologist Report |
Aug 01, 1995 | Permit Approved |
Aug 01, 1995 | Land Evidence Date |
Jan 13, 2010 | Correspondence Received |
Sep 13, 2010 | Modification Request |
Sep 13, 2010 | Administrative Review for Completeness |
Sep 17, 2010 | Team Review for Completeness |
Sep 17, 2010 | Team Review for Completeness |
Oct 07, 2010 | HPHC Historical Preservation No Effect |
Feb 01, 2011 | Additional Information Requested from Applicant |
Apr 06, 2011 | 30-Day Notification of Cancellation letter |
Apr 08, 2011 | Certified Receipt Received |
Apr 28, 2011 | Correspondence Received |
May 04, 2011 | Additional Information Requested from Applicant |
Jul 29, 2011 | Additional Information Received |
Sep 01, 2011 | Additional Information Received |
Sep 09, 2011 | 30 day Public Notice Issued |
Oct 09, 2011 | Public Notice End Date |
Dec 07, 2011 | Biologist Report |
Dec 07, 2011 | Engineering Report |
Dec 13, 2011 | Land Evidence Date |
Dec 28, 2011 | Modification Approved |
Dec 28, 2011 | Typist for Processing |
Dec 30, 2011 | Executive Sign Off |
Dec 30, 2011 | Sent to Photo Copy |
Jan 23, 2012 | Land Evidence Date |
Mar 19, 2012 | US Army Corps of Engineers Approval Received |