Action Date | Action Description |
---|---|
Assent Requirement | |
Jun 06, 1996 | Application Accepted |
Jun 13, 1996 | Historical Preservation Approval Granted |
Jul 31, 1996 | Engineering Report |
Aug 01, 1996 | Biologist Report |
Aug 05, 1996 | Permit Approved |
Aug 05, 1996 | Land Evidence Date |
Mar 05, 2018 | Modification Request |
Mar 15, 2018 | Administrative Review for Completeness |
Mar 15, 2018 | Team Review for Completeness |
Mar 15, 2018 | Application Accepted |
Apr 06, 2018 | HPHC Historical Preservation No Effect |
Apr 11, 2018 | Biologist Report |
Apr 11, 2018 | Typist for Processing |
Apr 11, 2018 | Executive Sign Off |
Apr 11, 2018 | Sent to Photo Copy |
Apr 11, 2018 | Modification Approved |
Apr 23, 2018 | Land Evidence Date |
Oct 15, 2018 | Additional Information Received |