Action Date | Action Description |
---|---|
Mar 17, 2004 | Application Accepted |
Mar 17, 2004 | Category B assigned |
Mar 31, 2004 | Historical Preservation Approval Granted |
Apr 02, 2004 | 30 day Public Notice Issued |
Aug 18, 2004 | Engineering Report |
Sep 10, 2004 | Biologist Report |
Sep 24, 2004 | Biologist Report |
Sep 28, 2004 | Meeting Held |
Sep 28, 2004 | Semi-Monthly Meeting Held |
Sep 28, 2004 | Council Approval Granted |
Mar 29, 2005 | Stipulation Package from Biologist |
Mar 30, 2005 | Stipulation Package by Engineer |
Mar 31, 2005 | Typist for Processing |
Mar 31, 2005 | Executive Sign Off |
Mar 31, 2005 | Sent to Photo Copy |
Mar 31, 2005 | Permit Approved |
Apr 12, 2005 | Biologist Report |
Apr 12, 2005 | Legal Response/Decision |
Apr 13, 2005 | Plans Received |
Apr 13, 2005 | Modification Approved |
Apr 26, 2005 | Land Evidence Date |
Mar 26, 2007 | Modification Request |
Mar 27, 2007 | Administrative Review for Completeness |
Apr 02, 2007 | Additional Information Received |
Apr 03, 2007 | Modification Canceled |
Apr 03, 2007 | Team Review for Completeness |