Action Date | Action Description |
---|---|
Jan 19, 2001 | ISDS Approved |
Aug 26, 2004 | Application Accepted |
Sep 22, 2004 | Biologist Report |
Sep 22, 2004 | Engineering Report |
Sep 27, 2004 | Historical Preservation Approval Granted |
Sep 28, 2004 | Permit Approved |
Sep 28, 2004 | Land Evidence Date |
Nov 16, 2005 | Assent Correction Mailed |
Dec 15, 2005 | Land Evidence Date |
Aug 07, 2007 | Extension of Permit Request |
Aug 16, 2007 | Enforcement Compliance Inspection Required |
Aug 21, 2007 | Process Extension |
Aug 21, 2007 | Typist for Processing |
Aug 21, 2007 | Executive Sign Off |
Aug 21, 2007 | Sent to Photo Copy |
Aug 21, 2007 | Extension Approved |
Aug 12, 2008 | Extension of Permit Request |
Dec 02, 2008 | Enforcement Compliance Inspection Required |
Dec 02, 2008 | Extension Approved |
Sep 04, 2009 | Extension of Permit Request |
Oct 06, 2009 | Enforcement Compliance Inspection Required |
Oct 07, 2009 | Process Extension |
Oct 07, 2009 | Typist for Processing |
Oct 07, 2009 | Executive Sign Off |
Oct 07, 2009 | Sent to Photo Copy |
Oct 07, 2009 | Extension Approved |
Oct 19, 2011 | Extension Toll letter mailed |