Action Date | Action Description |
---|---|
Sep 20, 2004 | Application Accepted |
Sep 22, 2004 | Engineering Report |
Sep 28, 2004 | 30 day Public Notice Issued |
Sep 28, 2004 | Meeting Held |
Oct 05, 2004 | Historical Preservation Approval Granted |
Oct 13, 2004 | Permit Approved |
Oct 13, 2004 | Land Evidence Date |
May 16, 2005 | Engineering Report |
May 19, 2005 | Executive Sign Off |
May 19, 2005 | Legal Response/Decision |
Apr 16, 2007 | Correspondence Received |
Apr 23, 2007 | Correspondence Mailed/Faxed/E-mailed |
Apr 27, 2007 | Extension of Permit Request |
Aug 16, 2007 | Enforcement Compliance Inspection Required |
Aug 21, 2007 | Process Extension |
Aug 21, 2007 | Typist for Processing |
Aug 21, 2007 | Executive Sign Off |
Aug 21, 2007 | Sent to Photo Copy |
Aug 21, 2007 | Extension Approved |
Aug 27, 2007 | Land Evidence Date |
Jun 30, 2008 | Extension of Permit Request |
Sep 08, 2008 | Enforcement Compliance Inspection Required |
Sep 09, 2008 | Process Extension |
Sep 09, 2008 | Extension Approved |
Jul 29, 2009 | Extension of Permit Request |
Sep 11, 2009 | Enforcement Compliance Inspection Required |
Sep 11, 2009 | Process Extension |
Sep 11, 2009 | Extension Approved |
Sep 20, 2010 | Extension of Permit Request |
Feb 25, 2011 | Extension Toll letter mailed |