Action Date | Action Description |
---|---|
Sep 27, 2004 | Application Accepted |
Oct 05, 2004 | Historical Preservation Approval Granted |
Dec 01, 2004 | 30 day Public Notice Issued |
Feb 23, 2005 | US Army Corp of Engineers Permit Date |
Feb 24, 2005 | US Army Corps of Engineers Approval Received |
May 26, 2005 | Supervisor Biologist SignOff |
May 26, 2005 | Supervisor Engineer SignOff |
May 26, 2005 | Stipulation Package from Biologist |
May 26, 2005 | Stipulation Package by Engineer |
Jun 01, 2005 | Executive Sign Off |
Jun 21, 2005 | Ready to Schedule Semi-Monthly Meeting |
Jun 21, 2005 | Mail Agenda Notice |
Jun 28, 2005 | Semi-Monthly Meeting Held |
Jun 28, 2005 | Council Approval Granted |
Jun 28, 2005 | Council Approval Granted |
Jun 28, 2005 | Semi-Monthly Meeting Date Scheduled |
Jul 12, 2005 | Stipulation Package from Biologist |
Jul 14, 2005 | Typist for Processing |
Jul 14, 2005 | Executive Sign Off |
Jul 14, 2005 | Sent to Photo Copy |
Jul 14, 2005 | Permit Approved |
Jul 27, 2005 | Land Evidence Date |
Jan 20, 2006 | Legal Response/Decision |