Action Date | Action Description |
---|---|
Feb 15, 2005 | Assent Application Received |
Feb 17, 2005 | Administrative Review for Completeness |
Feb 21, 2005 | Team Review for Completeness |
Feb 21, 2005 | Application Accepted |
Feb 24, 2005 | 30 day Public Notice Issued |
Mar 01, 2005 | HPHC Review Pending |
Mar 17, 2005 | Correspondence Received |
Mar 24, 2005 | Engineering Report |
Mar 24, 2005 | Biologist Report |
Mar 24, 2005 | Supervisor Biologist SignOff |
Mar 24, 2005 | Supervisor Engineer SignOff |
Mar 28, 2005 | Executive Sign Off |
Apr 15, 2005 | Ready to Schedule Semi-Monthly Meeting |
Apr 15, 2005 | Public Notice End Date |
Apr 15, 2005 | Mail Agenda Notice |
Apr 18, 2005 | Correspondence Received |
Apr 25, 2005 | US Army Corp of Engineers Permit Date |
Apr 26, 2005 | Semi-Monthly Meeting Held |
Apr 26, 2005 | Council Approval Granted |
Apr 26, 2005 | Semi-Monthly Meeting Date Scheduled |
Apr 27, 2005 | US Army Corps of Engineers Approval Received |
May 02, 2005 | Stipulation Package from Biologist |
May 02, 2005 | Stipulation Package by Engineer |
May 02, 2005 | Category B assigned |
May 04, 2005 | Typist for Processing |
May 04, 2005 | Sent to Photo Copy |
May 04, 2005 | Executive Sign Off |
May 04, 2005 | Permit Approved |
May 06, 2005 | Biologist Report |
May 09, 2005 | Legal Response/Decision |
May 10, 2005 | US Army Corp of Engineers Permit Date |
May 11, 2005 | US Army Corps of Engineers Approval Received |