Action Date | Action Description |
---|---|
May 26, 2005 | Assent Application Received |
May 27, 2005 | Administrative Review for Completeness |
Jun 13, 2005 | Team Review for Completeness |
Jun 13, 2005 | Application Accepted |
Sep 27, 2005 | Biologist Report |
Dec 23, 2005 | Supervisor Biologist SignOff |
Dec 23, 2005 | Plans Received |
Feb 07, 2006 | Plans Received |
Feb 27, 2006 | Executive Sign Off |
Feb 28, 2006 | Typist for Processing |
Feb 28, 2006 | Executive Sign Off |
Feb 28, 2006 | Sent to Photo Copy |
Feb 28, 2006 | Permit Approved |
Mar 03, 2006 | Land Evidence Date |
Apr 17, 2006 | Modification Request |
Apr 18, 2006 | Administrative Review for Completeness |
Apr 20, 2006 | Team Review for Completeness |
May 17, 2006 | Biologist Report |
May 17, 2006 | Typist for Processing |
May 17, 2006 | Executive Sign Off |
May 17, 2006 | Sent to Photo Copy |
May 17, 2006 | Modification Approved |
May 22, 2006 | Land Evidence Date |