Action Date | Action Description |
---|---|
Jun 21, 2005 | Assent Application Received |
Jun 22, 2005 | Administrative Review for Completeness |
Jun 27, 2005 | Deficient Application - Owner Notification Sent |
Jul 04, 2005 | Deficient Application Picked Up |
Aug 15, 2005 | Deficiency Response Received |
Aug 19, 2005 | Team Review for Completeness |
Aug 19, 2005 | Application Accepted |
Aug 19, 2005 | Category A* (Docks) |
Aug 19, 2005 | Category A* (Docks) |
Aug 26, 2005 | 30 day Public Notice Issued |
Sep 06, 2005 | HPHC Review Pending |
Oct 12, 2005 | Public Notice End Date |
Oct 17, 2005 | US Army Corp of Engineers Permit Date |
Oct 17, 2005 | Correspondence Received |
Oct 19, 2005 | US Army Corps of Engineers Approval Received |
Oct 24, 2005 | Biologist Report |
Oct 28, 2005 | Dock sub-committee Approved |
Oct 28, 2005 | 30 day Public Notice Issued |
Dec 13, 2005 | Correspondence Received |
Dec 15, 2005 | Public Notice End Date |
Jan 10, 2006 | Engineering Report |
Jan 11, 2006 | Typist for Processing |
Jan 11, 2006 | Executive Sign Off |
Jan 11, 2006 | Sent to Photo Copy |
Jan 11, 2006 | Permit Approved |
Feb 10, 2006 | Land Evidence Date |
Mar 21, 2006 | Commencement of Work Notice received |
Mar 31, 2011 | Modification Request |
Apr 01, 2011 | Administrative Review for Completeness |
Apr 05, 2011 | Team Review for Completeness |
Apr 07, 2011 | Team Review for Completeness |
Apr 11, 2011 | Deficient Application - Owner Notification Sent |
Jul 16, 2012 | Deficient Application Discarded/No deficiency Reponse |