Action Date | Action Description |
---|---|
Jun 29, 2005 | Assent Application Received |
Jun 29, 2005 | Administrative Review for Completeness |
Jul 07, 2005 | Team Review for Completeness |
Jul 07, 2005 | Application Accepted |
Jul 12, 2005 | HPHC Review Pending |
Jul 13, 2005 | Engineering Report |
Jul 13, 2005 | Typist for Processing |
Jul 13, 2005 | Executive Sign Off |
Jul 13, 2005 | Sent to Photo Copy |
Jul 13, 2005 | Permit Approved |
Jul 25, 2005 | Land Evidence Date |