Action Date | Action Description |
---|---|
Jul 26, 2005 | Assent Application Received |
Aug 02, 2005 | Deficient Application - Owner Notification Sent |
Sep 19, 2005 | Deficient Application Picked Up |
Sep 19, 2005 | Deficiency Response Received |
Sep 20, 2005 | Deficient Application - Owner Notification Sent |
Nov 15, 2005 | Deficiency Response Received |
Nov 23, 2005 | Team Review for Completeness |
Nov 23, 2005 | Application Accepted |
Nov 23, 2005 | Category A* (Docks) |
Dec 12, 2005 | 30 day Public Notice Issued |
Dec 19, 2005 | HPHC Historical Preservation No Effect |
Feb 16, 2006 | Objections/Comments Received |
Feb 20, 2006 | Public Notice End Date |
Feb 24, 2006 | Dock Subcommittee Meeting Held |
Mar 03, 2006 | Typist for Processing |
Mar 03, 2006 | Dock sub-committee Approved |
Mar 03, 2006 | Dock Subcommittee Meeting Held |
Mar 03, 2006 | Executive Sign Off |
Mar 03, 2006 | Sent to Photo Copy |
Mar 03, 2006 | Permit Approved |
Mar 03, 2006 | Biologist Report |
Mar 03, 2006 | Engineering Report |
Mar 07, 2006 | US Army Corp of Engineers Permit Date |
Mar 13, 2006 | US Army Corps of Engineers Approval Received |
Apr 06, 2006 | Land Evidence Date |
Nov 26, 2008 | Extension of Permit Request |
Dec 03, 2008 | Enforcement Compliance Inspection Required |
Dec 03, 2008 | Extension Approved |