Action Date | Action Description |
---|---|
Sep 06, 2005 | Assent Application Received |
Sep 07, 2005 | Administrative Review for Completeness |
Sep 07, 2005 | Category A* (Docks) |
Sep 26, 2005 | Team Review for Completeness |
Sep 26, 2005 | Application Accepted |
Oct 05, 2005 | HPHC Review Pending |
Oct 05, 2005 | Historical Preservation Approval Granted |
Nov 02, 2005 | 30 day Public Notice Issued |
Jan 11, 2006 | US Army Corp of Engineers Permit Date |
Jan 12, 2006 | US Army Corps of Engineers Approval Received |
Jan 13, 2006 | Public Notice End Date |
Jan 27, 2006 | Engineering Report |
Jan 27, 2006 | Dock sub-committee Approved |
Jan 31, 2006 | Biologist Report |
Feb 01, 2006 | Typist for Processing |
Feb 01, 2006 | Executive Sign Off |
Feb 01, 2006 | Sent to Photo Copy |
Feb 01, 2006 | Permit Approved |
Feb 10, 2006 | Land Evidence Date |