Action Date | Action Description |
---|---|
Nov 07, 2005 | Assent Application Received |
Nov 08, 2005 | Administrative Review for Completeness |
Nov 21, 2005 | Deficient Application - Owner Notification Sent |
Dec 23, 2005 | Deficiency Response Received |
Jan 10, 2006 | Deficient Application - Owner Notification Sent |
Mar 17, 2006 | Deficiency Response Received |
Mar 24, 2006 | Team Review for Completeness |
Mar 24, 2006 | Application Accepted |
Mar 24, 2006 | Category B assigned |
Apr 03, 2006 | HPHC Historical Preservation No Effect |
Apr 06, 2006 | 30 day Public Notice Issued |
May 11, 2006 | Additional Information Received |
Jun 16, 2006 | Correspondence Received |
Jun 19, 2006 | Public Notice End Date |
Oct 17, 2006 | Plans Received |
Nov 28, 2006 | Biologist Report |
Nov 28, 2006 | Engineering Report |
Nov 29, 2006 | Supervisor Engineer SignOff |
Nov 29, 2006 | Supervisor Biologist SignOff |
Nov 30, 2006 | Executive Sign Off |
Dec 04, 2006 | US Army Corp of Engineers Permit Date |
Dec 07, 2006 | US Army Corps of Engineers Approval Received |
Jan 26, 2007 | Typist for Processing |
Jan 26, 2007 | Executive Sign Off |
Jan 26, 2007 | Sent to Photo Copy |
Jan 26, 2007 | Permit Approved |
Jun 07, 2007 | Land Evidence Date |
Jun 18, 2007 | Commencement of Work Notice received |