Action Date | Action Description |
---|---|
Dec 05, 2005 | Assent Application Received |
Dec 07, 2005 | Administrative Review for Completeness |
Dec 30, 2005 | Team Review for Completeness |
Dec 30, 2005 | Application Accepted |
Dec 30, 2005 | Category A* (Docks) |
Jan 04, 2006 | 30 day Public Notice Issued |
Jan 10, 2006 | HPHC Historical Preservation No Effect |
Feb 17, 2006 | Public Notice End Date |
Mar 15, 2006 | Certified Receipt Received |
Mar 16, 2006 | Engineering Report |
Mar 21, 2006 | Biologist Report |
Mar 27, 2006 | US Army Corp of Engineers Permit Date |
Apr 03, 2006 | US Army Corps of Engineers Approval Received |
Apr 12, 2006 | Supervisor Biologist SignOff |
Apr 12, 2006 | Supervisor Engineer SignOff |
Apr 12, 2006 | Executive Sign Off |
Apr 19, 2006 | Mail Agenda Notice |
Apr 25, 2006 | Semi-Monthly Meeting Date Scheduled |
Apr 28, 2006 | Ready to Schedule Semi-Monthly Meeting |
Apr 28, 2006 | Mail Agenda Notice |
May 09, 2006 | Council Approval Granted |
May 09, 2006 | Semi-Monthly Meeting Held |
May 09, 2006 | Semi-Monthly Meeting Date Scheduled |
May 15, 2006 | Typist for Processing |
May 15, 2006 | Executive Sign Off |
May 15, 2006 | Sent to Photo Copy |
May 15, 2006 | Permit Approved |
May 15, 2006 | Stipulation Package from Biologist |
May 15, 2006 | Stipulation Package by Engineer |
May 19, 2006 | Legal Response/Decision |
Sep 01, 2006 | Land Evidence Date |