Action Date | Action Description |
---|---|
Commencement of Work Notice received | |
Dec 09, 2005 | Assent Application Received |
Dec 09, 2005 | Administrative Review for Completeness |
Dec 12, 2005 | Deficient Application Picked Up |
Dec 13, 2005 | Deficiency Response Received |
Dec 15, 2005 | Team Review for Completeness |
Dec 15, 2005 | Application Accepted |
Jan 01, 2006 | HPHC Historical Preservation No Effect |
Jan 31, 2006 | Typist for Processing |
Jan 31, 2006 | Executive Sign Off |
Jan 31, 2006 | Sent to Photo Copy |
Jan 31, 2006 | Permit Approved |
Jan 31, 2006 | Biologist Report |
Jan 31, 2006 | Engineering Report |
Feb 21, 2006 | Land Evidence Date |