Action Date | Action Description |
---|---|
Jan 10, 2006 | Assent Application Received |
Jan 10, 2006 | Administrative Review for Completeness |
Jan 24, 2006 | Team Review for Completeness |
Jan 24, 2006 | Application Accepted |
Jan 26, 2006 | Category B assigned |
Feb 10, 2006 | HPHC Historical Preservation No Effect |
Feb 16, 2006 | 30 day Public Notice Issued |
Mar 06, 2006 | Engineering Report |
Mar 15, 2006 | Correspondence Received |
Mar 18, 2006 | Public Notice End Date |
Mar 22, 2006 | Additional Information Requested from Applicant |
Jun 02, 2006 | Additional Information Requested from Applicant |
Jun 15, 2006 | Plans Received |
Jul 14, 2006 | Plans Received |
Aug 22, 2006 | Additional Information Requested from Applicant |
Feb 05, 2007 | 30-Day Notification of Cancellation letter |
Feb 13, 2007 | Plans Received |
Apr 18, 2007 | Biologist Report |
Apr 19, 2007 | Typist for Processing |
Apr 19, 2007 | Executive Sign Off |
Apr 19, 2007 | Sent to Photo Copy |
Apr 19, 2007 | Permit Approved |
May 04, 2007 | Land Evidence Date |
Jan 20, 2010 | Extension of Permit Request |
Apr 07, 2010 | Enforcement Compliance Inspection Required |
Apr 08, 2010 | Violation Exists on this Site (C&D Order) |
Apr 08, 2010 | Extension Toll letter mailed |
Apr 19, 2011 | Extension of Permit Request |
Apr 19, 2011 | Extension Toll letter mailed |
Sep 12, 2011 | Extension Toll letter mailed |
Nov 15, 2013 | Extension Toll letter mailed |
Sep 08, 2015 | Extension Toll letter mailed |