Action Date | Action Description |
---|---|
Jan 17, 2006 | Assent Application Received |
Jan 17, 2006 | Administrative Review for Completeness |
Jan 25, 2006 | Deficient Application - Owner Notification Sent |
Feb 13, 2006 | Deficiency Response Received |
Feb 15, 2006 | Team Review for Completeness |
Feb 15, 2006 | Category A* (Docks) |
Mar 10, 2006 | 30 day Public Notice Issued |
Mar 22, 2006 | Correspondence Received |
May 01, 2006 | Correspondence Received |
May 01, 2006 | Public Notice End Date |
May 03, 2006 | Correspondence Received |
May 11, 2006 | Biologist Report |
May 11, 2006 | Engineering Report |
May 23, 2006 | US Army Corp of Engineers Permit Date |
May 25, 2006 | US Army Corps of Engineers Approval Received |
Oct 31, 2006 | Supervisor Biologist SignOff |
Oct 31, 2006 | Supervisor Engineer SignOff |
Nov 02, 2006 | Executive Sign Off |
Jan 22, 2007 | Typist for Processing |
Jan 22, 2007 | Executive Sign Off |
Jan 22, 2007 | Sent to Photo Copy |
Jan 22, 2007 | Permit Approved |
Feb 07, 2007 | Land Evidence Date |
May 10, 2007 | Commencement of Work Notice received |