Action Date | Action Description |
---|---|
Jan 25, 2006 | Assent Application Received |
Jan 26, 2006 | Administrative Review for Completeness |
Feb 01, 2006 | Team Review for Completeness |
Feb 01, 2006 | Application Accepted |
Feb 02, 2006 | Category B assigned |
Feb 07, 2006 | 30 day Public Notice Issued |
Feb 15, 2006 | HPHC Historical Preservation No Effect |
Feb 17, 2006 | Correspondence Received |
Mar 06, 2006 | Engineering Report |
Mar 15, 2006 | Correspondence Received |
Mar 17, 2006 | Public Notice End Date |
Apr 24, 2006 | US Army Corp of Engineers Permit Date |
May 01, 2006 | US Army Corps of Engineers Approval Received |
May 03, 2006 | Biologist Report |
May 08, 2006 | Supervisor Biologist SignOff |
May 08, 2006 | Supervisor Engineer SignOff |
May 09, 2006 | Executive Sign Off |
May 11, 2006 | Ready to Schedule Semi-Monthly Meeting |
May 11, 2006 | Mail Agenda Notice |
May 23, 2006 | Council Approval Granted |
May 23, 2006 | Semi-Monthly Meeting Date Scheduled |
May 25, 2006 | Stipulation Package from Biologist |
May 25, 2006 | Stipulation Package by Engineer |
May 26, 2006 | Typist for Processing |
May 26, 2006 | Executive Sign Off |
May 26, 2006 | Sent to Photo Copy |
May 26, 2006 | Permit Approved |
Jun 12, 2006 | Legal Response/Decision |
Sep 06, 2006 | Land Evidence Date |