Action Date | Action Description |
---|---|
Legal Response/Decision | |
Apr 25, 2006 | Assent Application Received |
Apr 26, 2006 | Administrative Review for Completeness |
May 01, 2006 | Team Review for Completeness |
May 01, 2006 | Application Accepted |
May 03, 2006 | Category B assigned |
May 11, 2006 | 30 day Public Notice Issued |
May 12, 2006 | HPHC Historical Preservation No Effect |
Jun 30, 2006 | Public Notice End Date |
Jul 05, 2006 | Correspondence Received |
Jul 13, 2006 | Engineering Report |
Jul 19, 2006 | Additional Information Received |
Aug 01, 2006 | US Army Corp of Engineers Permit Date |
Aug 04, 2006 | US Army Corps of Engineers Approval Received |
Aug 16, 2006 | Biologist Report |
Sep 19, 2006 | Supervisor Biologist SignOff |
Sep 19, 2006 | Supervisor Engineer SignOff |
Sep 20, 2006 | Executive Sign Off |
Oct 31, 2006 | Ready to Schedule Semi-Monthly Meeting |
Oct 31, 2006 | Mail Agenda Notice |
Nov 14, 2006 | Semi-Monthly Meeting Date Scheduled |
Nov 14, 2006 | Semi-Monthly Meeting Held |
Nov 14, 2006 | Council Approval Granted |
Nov 20, 2006 | Stipulation Package by Engineer |
Nov 21, 2006 | Stipulation Package from Biologist |
Nov 22, 2006 | Typist for Processing |
Nov 22, 2006 | Executive Sign Off |
Nov 22, 2006 | Sent to Photo Copy |
Nov 22, 2006 | Permit Approved |
Jan 10, 2007 | Land Evidence Date |
Jan 10, 2007 | Correspondence Mailed/Faxed/E-mailed |
Aug 25, 2010 | Modification Request |
Aug 31, 2010 | Administrative Review for Completeness |