Action Date | Action Description |
---|---|
Jun 02, 2006 | Assent Application Received |
Jun 02, 2006 | Administrative Review for Completeness |
Jun 02, 2006 | Team Review for Completeness |
Jun 02, 2006 | Application Accepted |
Jun 23, 2006 | Engineering Report |
Jun 23, 2006 | Executive Sign Off |
Jun 23, 2006 | Sent to Photo Copy |
Jun 23, 2006 | Permit Approved |
Jun 23, 2006 | HPHC Historical Preservation No Effect |
Jun 26, 2006 | Typist for Processing |
Jul 10, 2006 | Land Evidence Date |
Aug 29, 2006 | Correspondence Received |
Feb 07, 2007 | Modification Request |
Feb 09, 2007 | Administrative Review for Completeness |
Feb 09, 2007 | Team Review for Completeness |
Feb 09, 2007 | Team Review for Completeness |
Feb 09, 2007 | Typist for Processing |
Feb 09, 2007 | Executive Sign Off |
Feb 09, 2007 | Sent to Photo Copy |
Feb 09, 2007 | Modification Approved |
Feb 14, 2007 | Land Evidence Date |