Action Date | Action Description |
---|---|
Monitoring Report | |
Jun 26, 2006 | Assent Application Received |
Jun 27, 2006 | Administrative Review for Completeness |
Jul 14, 2006 | Team Review for Completeness |
Jul 14, 2006 | Application Accepted |
Jul 14, 2006 | Category B assigned |
Jul 27, 2006 | 30 day Public Notice Issued |
Aug 24, 2006 | Meeting Held |
Aug 27, 2006 | Public Notice End Date |
Nov 20, 2006 | Plans Received |
Dec 20, 2006 | HPHC Historical Preservation Comments/Concerns |
Dec 21, 2006 | HPHC Historical Preservation Comments/Concerns |
Mar 09, 2007 | Additional Information Received |
Apr 09, 2007 | Engineering Report |
Apr 16, 2007 | US Army Corp of Engineers Permit Date |
Apr 18, 2007 | US Army Corps of Engineers Approval Received |
Jul 02, 2007 | Correspondence Received |
Jul 23, 2007 | Plans Received |
Jul 27, 2007 | Public Hearing Notices Mailed |
Jul 30, 2007 | Water Quality Certification |
Aug 03, 2007 | Biologist Report |
Aug 28, 2007 | Special Exception Scheduled for Semi-Monthly |
Aug 28, 2007 | Semi-Monthly Meeting Held |
Aug 28, 2007 | Council Approval Granted |
Sep 05, 2007 | Legal Response/Decision |
Sep 11, 2007 | Stipulation Package from Biologist |
Sep 12, 2007 | Stipulation Package by Engineer |
Sep 12, 2007 | Permit Approved |
Sep 12, 2007 | Typist for Processing |
Sep 12, 2007 | Executive Sign Off |
Sep 12, 2007 | Sent to Photo Copy |
Sep 21, 2007 | Land Evidence Date |
Oct 17, 2007 | Correspondence Received |
Dec 17, 2007 | Monitoring Report |
Jan 04, 2008 | Monitoring Report |
Mar 11, 2008 | Monitoring Report |
Apr 29, 2008 | Monitoring Report |
May 22, 2008 | Modification Request |
May 23, 2008 | Administrative Review for Completeness |
May 29, 2008 | Team Review for Completeness |
May 29, 2008 | Engineering Report |
May 29, 2008 | Typist for Processing |
May 29, 2008 | Executive Sign Off |
May 29, 2008 | Sent to Photo Copy |
May 29, 2008 | Modification Approved |
Jun 05, 2008 | Land Evidence Date |
Jun 06, 2008 | Monitoring Report |
Aug 18, 2008 | Monitoring Report |
Aug 19, 2009 | Monitoring Report |
Mar 10, 2010 | Monitoring Report |
May 13, 2010 | Monitoring Report |
May 24, 2010 | Letter of Authorization |
Aug 11, 2010 | Monitoring Report |
Aug 13, 2010 | Additional Information Received |
Nov 18, 2010 | Monitoring Report |