Action Date | Action Description |
---|---|
Jul 25, 2006 | Assent Application Received |
Jul 26, 2006 | Administrative Review for Completeness |
Jul 28, 2006 | Team Review for Completeness |
Jul 28, 2006 | Application Accepted |
Aug 10, 2006 | Historical Preservation Conditional Approval |
Oct 06, 2006 | Plans Received |
Oct 16, 2006 | Correspondence Received |
Oct 31, 2006 | Historical Preservation Conditional Approval |
Oct 31, 2006 | Engineering Report |
Oct 31, 2006 | HPHC Historical Preservation No Effect |
Nov 01, 2006 | Typist for Processing |
Nov 01, 2006 | Executive Sign Off |
Nov 01, 2006 | Sent to Photo Copy |
Nov 01, 2006 | Permit Approved |
Nov 17, 2006 | Commencement of Work Notice received |
Nov 22, 2006 | Land Evidence Date |