Action Date | Action Description |
---|---|
Aug 04, 2006 | Assent Application Received |
Aug 04, 2006 | Administrative Review for Completeness |
Aug 10, 2006 | Team Review for Completeness |
Aug 10, 2006 | Application Accepted |
Aug 22, 2006 | 30 day Public Notice Issued |
Aug 25, 2006 | HPHC Historical Preservation No Effect |
Oct 13, 2006 | Public Notice End Date |
Nov 20, 2006 | US Army Corp of Engineers Permit Date |
Nov 27, 2006 | US Army Corps of Engineers Approval Received |
Dec 01, 2006 | Dock Meeting Scheduled (Admin) |
Dec 01, 2006 | Dock sub-committee Approved |
Dec 04, 2006 | Engineering Report |
Dec 05, 2006 | Biologist Report |
Dec 05, 2006 | Typist for Processing |
Dec 05, 2006 | Executive Sign Off |
Dec 05, 2006 | Sent to Photo Copy |
Dec 05, 2006 | Permit Approved |
Jan 02, 2007 | Land Evidence Date |
Jan 05, 2007 | Category A* (Docks) |
Oct 09, 2007 | Commencement of Work Notice received |