Action Date | Action Description |
---|---|
Sep 12, 2006 | Assent Application Received |
Sep 12, 2006 | Administrative Review for Completeness |
Sep 15, 2006 | Team Review for Completeness |
Sep 15, 2006 | Application Accepted |
Sep 15, 2006 | Category A* (Docks) |
Sep 28, 2006 | HPHC Historical Preservation No Effect |
Oct 06, 2006 | 30 day Public Notice Issued |
Dec 13, 2006 | Public Notice End Date |
Dec 15, 2006 | Correspondence Received |
Jan 04, 2007 | US Army Corp of Engineers Permit Date |
Jan 08, 2007 | US Army Corps of Engineers Approval Received |
Jan 31, 2007 | Biologist Report |
Jan 31, 2007 | Engineering Report |
Feb 07, 2007 | Dock Meeting -- Approval |
Feb 13, 2007 | Typist for Processing |
Feb 13, 2007 | Executive Sign Off |
Feb 13, 2007 | Sent to Photo Copy |
Feb 13, 2007 | Permit Approved |
Feb 15, 2007 | Land Evidence Date |
Mar 08, 2007 | Category A* (Docks) |
Oct 01, 2019 | Correspondence Mailed/Faxed/E-mailed |