Action Date | Action Description |
---|---|
Sep 25, 2006 | Assent Application Received |
Sep 26, 2006 | Administrative Review for Completeness |
Oct 02, 2006 | Deficient Application - Owner Notification Sent |
Oct 02, 2006 | Deficient Application Picked Up |
Oct 03, 2006 | Deficiency Response Received |
Oct 04, 2006 | Administrative Review for Completeness |
Oct 06, 2006 | Team Review for Completeness |
Oct 06, 2006 | Application Accepted |
Jan 08, 2007 | Biologist Report |
Jan 08, 2007 | Engineering Report |
Jan 08, 2007 | Typist for Processing |
Jan 08, 2007 | Executive Sign Off |
Jan 08, 2007 | Sent to Photo Copy |
Jan 08, 2007 | Permit Approved |
Jan 12, 2007 | Land Evidence Date |
Feb 12, 2014 | Extension Toll letter mailed |
Nov 12, 2014 | Note to File |