Action Date | Action Description |
---|---|
Nov 09, 2006 | Assent Application Received |
Nov 10, 2006 | Administrative Review for Completeness |
Nov 20, 2006 | Deficient Application - Owner Notification Sent |
Dec 28, 2006 | Deficiency Response Received |
Dec 28, 2006 | Administrative Review for Completeness |
Jan 02, 2007 | Team Review for Completeness |
Jan 02, 2007 | Application Accepted |
Jan 22, 2007 | HPHC Historical Preservation No Effect |
Feb 14, 2007 | Typist for Processing |
Feb 14, 2007 | Executive Sign Off |
Feb 14, 2007 | Sent to Photo Copy |
Feb 14, 2007 | Permit Approved |
Feb 14, 2007 | Biologist Report |
Feb 26, 2007 | Land Evidence Date |
Dec 06, 2007 | Correspondence Received |
Jan 03, 2008 | Correspondence Mailed/Faxed/E-mailed |
Jan 07, 2008 | Correspondence Received |
Jan 08, 2008 | Correspondence Mailed/Faxed/E-mailed |