Action Date |
Action Description |
Nov 17, 2006 |
Assent Application Received |
Nov 17, 2006 |
Administrative Review for Completeness |
Dec 01, 2006 |
Deficient Application - Owner Notification Sent |
Jan 04, 2007 |
Deficient Application Picked Up |
Mar 19, 2007 |
Deficiency Response Received |
Mar 19, 2007 |
Administrative Review for Completeness |
Mar 27, 2007 |
Team Review for Completeness |
Mar 27, 2007 |
Application Accepted |
Mar 30, 2007 |
Category B assigned |
Apr 03, 2007 |
30 day Public Notice Issued |
Apr 11, 2007 |
HPHC Historical Preservation No Effect |
Apr 30, 2007 |
Objections/Comments Received |
Apr 30, 2007 |
Correspondence Received |
May 02, 2007 |
Objections/Comments Received |
May 02, 2007 |
Objections/Comments Received |
May 03, 2007 |
Correspondence Mailed/Faxed/E-mailed |
May 31, 2007 |
Public Notice End Date |
May 31, 2007 |
Public Notice End Date Extension Granted |
Jul 05, 2007 |
Plans Received |
Aug 23, 2007 |
US Army Corp of Engineers Permit Date |
Aug 29, 2007 |
US Army Corps of Engineers Approval Received |
Sep 10, 2007 |
Engineering Report |
Dec 12, 2007 |
Correspondence Received |
Apr 07, 2008 |
30 day Public Notice Issued |
May 07, 2008 |
Public Notice End Date |
Aug 18, 2008 |
Engineering Report |
Aug 28, 2008 |
Biologist Report |
Aug 29, 2008 |
Supervisor Engineer SignOff |
Sep 26, 2008 |
Executive Signoff of Staff Reports |
Sep 26, 2008 |
Supervisor Biologist SignOff |
Oct 29, 2008 |
Ready to Schedule Semi-Monthly Meeting |
Feb 05, 2009 |
Mail Agenda Notice |
Feb 24, 2009 |
Semi-Monthly Meeting Postponed |
Feb 24, 2009 |
Semi-Monthly Meeting Date Scheduled |
Feb 24, 2009 |
Mail Agenda Notice |
Mar 24, 2009 |
Semi-Monthly Meeting Postponed |
Mar 24, 2009 |
Semi-Monthly Meeting Date Scheduled |
Mar 26, 2009 |
Mail Agenda Notice |
Mar 31, 2009 |
Mail Agenda Notice |
Apr 07, 2009 |
Council Approval Granted |
Apr 07, 2009 |
Semi-Monthly Meeting Date Scheduled |
Apr 07, 2009 |
Semi-Monthly Meeting Held |
Apr 21, 2009 |
Typist for Processing |
Apr 21, 2009 |
Executive Sign Off |
Apr 21, 2009 |
Sent to Photo Copy |
Apr 21, 2009 |
Permit Approved |
Apr 21, 2009 |
Stipulation Package from Biologist |
Apr 21, 2009 |
Stipulation Package by Engineer |
May 05, 2009 |
Assent Correction Request Received |
May 05, 2009 |
Assent Correction Mailed |
May 18, 2009 |
Land Evidence Date |
Jan 27, 2010 |
Legal Response/Decision |
Jun 30, 2011 |
Extension Toll letter mailed |
Jul 05, 2011 |
Correspondence Received |