Action Date | Action Description |
---|---|
Mar 16, 2007 | Assent Application Received |
Mar 19, 2007 | Administrative Review for Completeness |
Mar 19, 2007 | Team Review for Completeness |
Mar 19, 2007 | Team Review for Completeness |
Mar 19, 2007 | Application Accepted |
Mar 29, 2007 | Additional Information Received |
Mar 29, 2007 | HPHC Historical Preservation No Effect |
Apr 02, 2007 | Typist for Processing |
Apr 02, 2007 | Biologist Report |
Apr 02, 2007 | Engineering Report |
Apr 03, 2007 | Executive Sign Off |
Apr 03, 2007 | Sent to Photo Copy |
Apr 04, 2007 | Permit Approved |
Apr 06, 2007 | Commencement of Work Notice received |
Apr 11, 2007 | Land Evidence Date |
Apr 11, 2007 | Land Evidence Date |
Apr 25, 2007 | Modification Request |
Apr 26, 2007 | Administrative Review for Completeness |
Apr 30, 2007 | Team Review for Completeness |
Apr 30, 2007 | Team Review for Completeness |
Apr 30, 2007 | Typist for Processing |
Apr 30, 2007 | Executive Sign Off |
Apr 30, 2007 | Sent to Photo Copy |
Apr 30, 2007 | Modification Approved |
Jul 18, 2007 | Correspondence Mailed/Faxed/E-mailed |
Oct 01, 2007 | Correspondence Mailed/Faxed/E-mailed |
Nov 20, 2007 | Correspondence Received |
Nov 20, 2007 | Correspondence Received |
Apr 16, 2008 | Modification Request |
Apr 16, 2008 | Administrative Review for Completeness |
Apr 28, 2008 | Team Review for Completeness |
Apr 28, 2008 | Team Review for Completeness |
May 02, 2008 | Biologist Report |
May 02, 2008 | Engineering Report |
May 05, 2008 | Typist for Processing |
May 05, 2008 | Executive Sign Off |
May 05, 2008 | Sent to Photo Copy |
May 05, 2008 | Modification Approved |
May 29, 2008 | HPHC Historical Preservation No Effect |