Action Date | Action Description |
---|---|
Nov 30, 2007 | Assent Application Received |
Dec 03, 2007 | Administrative Review for Completeness |
Dec 07, 2007 | Plans Received |
Feb 20, 2008 | Deficient Application - Owner Notification Sent |
Feb 20, 2008 | Team Review for Completeness |
Mar 17, 2008 | Plans Received |
Mar 26, 2008 | Deficiency Response Received |
Mar 26, 2008 | Administrative Review for Completeness |
Apr 15, 2008 | Team Review for Completeness |
Apr 16, 2008 | Team Review for Completeness |
Apr 16, 2008 | Application Accepted |
May 05, 2008 | HPHC Historical Preservation No Effect |
May 06, 2008 | 30 day Public Notice Issued |
Jun 06, 2008 | Public Notice End Date |
Jun 19, 2008 | Executive Sign Off |
Jun 19, 2008 | Sent to Photo Copy |
Jun 26, 2008 | Permit Approved |
Jun 26, 2008 | Biologist Report |
Jun 26, 2008 | Engineering Report |
Jun 26, 2008 | Typist for Processing |
Jul 07, 2008 | US Army Corp of Engineers Permit Date |
Jul 08, 2008 | Land Evidence Date |
Jul 10, 2008 | US Army Corps of Engineers Approval Received |