Action Date | Action Description |
---|---|
Jan 24, 2008 | Assent Application Received |
Jan 28, 2008 | Administrative Review for Completeness |
Feb 25, 2008 | Team Review for Completeness |
Feb 25, 2008 | Deficient Application - Owner Notification Sent |
Apr 07, 2008 | Deficiency Response Received |
May 09, 2008 | Administrative Review for Completeness |
May 12, 2008 | Team Review for Completeness |
May 12, 2008 | Application Accepted |
May 12, 2008 | Category A* (Docks) |
May 21, 2008 | 30 day Public Notice Issued |
May 22, 2008 | HPHC Historical Preservation No Effect |
Jun 21, 2008 | Public Notice End Date |
Jul 16, 2008 | Dock Meeting -- Approval |
Jul 18, 2008 | Engineering Report |
Jul 23, 2008 | Typist for Processing |
Jul 23, 2008 | Executive Sign Off |
Jul 23, 2008 | Sent to Photo Copy |
Jul 23, 2008 | Permit Approved |
Jul 23, 2008 | Biologist Report |
Aug 04, 2008 | Land Evidence Date |
Aug 05, 2008 | US Army Corp of Engineers Permit Date |
Aug 07, 2008 | US Army Corps of Engineers Approval Received |