Action Date | Action Description |
---|---|
Mar 18, 2008 | Assent Application Received |
Mar 19, 2008 | Administrative Review for Completeness |
Mar 24, 2008 | Team Review for Completeness |
Mar 27, 2008 | Application Accepted |
Mar 27, 2008 | Team Review for Completeness |
Mar 27, 2008 | Category A* (Docks) |
May 02, 2008 | 30 day Public Notice Issued |
May 05, 2008 | HPHC Historical Preservation No Effect |
Jun 01, 2008 | Public Notice End Date |
Jun 25, 2008 | Engineering Report |
Jun 26, 2008 | Typist for Processing |
Jun 26, 2008 | Executive Sign Off |
Jun 26, 2008 | Sent to Photo Copy |
Jun 26, 2008 | Biologist Report |
Jun 30, 2008 | Permit Approved |
Jul 03, 2008 | Land Evidence Date |
Jul 14, 2008 | US Army Corps of Engineers Approval Received |
Jul 18, 2008 | US Army Corps of Engineers Approval Received |
Aug 13, 2008 | Modification Request |
Aug 19, 2008 | Administrative Review for Completeness |
Aug 19, 2008 | Team Review for Completeness |
Oct 01, 2008 | 30 day Public Notice Issued |
Oct 31, 2008 | Public Notice End Date |
Nov 03, 2008 | Dock Meeting -- Approval |
Dec 11, 2008 | Typist for Processing |
Dec 11, 2008 | Executive Sign Off |
Dec 11, 2008 | Sent to Photo Copy |
Dec 11, 2008 | Modification Approved |
Dec 11, 2008 | Engineering Report |
Jan 27, 2009 | Land Evidence Date |
Feb 14, 2022 | Modification Request |
Feb 17, 2022 | Administrative Review for Completeness |
Mar 07, 2022 | Eng Team Review for Completeness |
Mar 10, 2022 | Deficient Application Picked Up |
Apr 29, 2022 | Deficiency Response Received |
May 18, 2022 | Eng Team Review for Completeness |
May 19, 2022 | Additional Information Received |
Jun 02, 2022 | HPHC Historical Preservation No Effect |
Jun 02, 2022 | HPHC Review Pending |
Jun 07, 2022 | Additional Information Requested from Applicant |
Jun 16, 2022 | Additional Information Received |
Jul 07, 2022 | 30 day Public Notice Issued |
Jul 13, 2022 | US Army Corp of Engineers Permit Date |
Aug 07, 2022 | Public Notice End Date |
Nov 03, 2022 | Plans Received |
Nov 08, 2022 | Engineering Report |
Nov 15, 2022 | Typist for Processing |
Nov 15, 2022 | Executive Sign Off |
Nov 15, 2022 | Sent to Photo Copy |
Nov 15, 2022 | Modification Approved |
Nov 16, 2022 | Permit Mailed |