Action Date | Action Description |
---|---|
Aug 18, 2008 | Assent Application Received |
Aug 19, 2008 | Administrative Review for Completeness |
Sep 02, 2008 | Team Review for Completeness |
Sep 02, 2008 | Application Accepted |
Sep 02, 2008 | Category A* (Docks) |
Sep 12, 2008 | HPHC Historical Preservation No Effect |
Dec 03, 2008 | 30 day Public Notice Issued |
Jan 02, 2009 | Public Notice End Date |
Feb 13, 2009 | Plans Received |
Mar 23, 2009 | Dock Meeting -- Approval |
Mar 23, 2009 | US Army Corp of Engineers Permit Date |
Mar 23, 2009 | Biologist Report |
Mar 25, 2009 | US Army Corps of Engineers Approval Received |
Mar 27, 2009 | Typist for Processing |
Mar 27, 2009 | Executive Sign Off |
Mar 27, 2009 | Sent to Photo Copy |
Mar 27, 2009 | Permit Approved |
Mar 27, 2009 | Engineering Report |
Apr 17, 2009 | Land Evidence Date |
Jul 17, 2009 | Modification Request |
Jul 22, 2009 | Administrative Review for Completeness |
Jul 29, 2009 | Team Review for Completeness |
Jul 29, 2009 | Team Review for Completeness |
Aug 04, 2009 | Biologist Report |
Aug 04, 2009 | Engineering Report |
Aug 06, 2009 | Typist for Processing |
Aug 06, 2009 | Modification Approved |
Aug 10, 2009 | Executive Sign Off |
Aug 11, 2009 | Sent to Photo Copy |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
Oct 13, 2009 | Commencement of Work Notice received |