Action Date | Action Description |
---|---|
Jul 29, 2009 | Assent Application Received |
Jul 30, 2009 | Administrative Review for Completeness |
Aug 12, 2009 | Team Review for Completeness |
Aug 12, 2009 | Application Accepted |
Aug 27, 2009 | HPHC Historical Preservation No Effect |
Oct 15, 2009 | Typist for Processing |
Oct 15, 2009 | Executive Sign Off |
Oct 15, 2009 | Sent to Photo Copy |
Oct 15, 2009 | Permit Approved |
Oct 15, 2009 | Engineering Report |
Oct 20, 2009 | Land Evidence Date |
Nov 23, 2009 | US Army Corps of Engineers Approval Received |