Action Date |
Action Description |
Oct 14, 2009 |
Assent Application Received |
Oct 14, 2009 |
Administrative Review for Completeness |
Oct 20, 2009 |
Team Review for Completeness |
Oct 20, 2009 |
Application Accepted |
Oct 20, 2009 |
Category B assigned |
Dec 03, 2009 |
Additional Information Received |
Dec 08, 2009 |
30 day Public Notice Issued |
Dec 18, 2009 |
Special Exception Public Hearing Notice mailed |
Dec 30, 2009 |
Objections/Comments Received |
Dec 31, 2009 |
Objections/Comments Received |
Dec 31, 2009 |
Entry of Appearance Received |
Dec 31, 2009 |
HPHC Historical Preservation Comments/Concerns |
Jan 04, 2010 |
Objections/Comments Received |
Jan 05, 2010 |
Objections/Comments Received |
Jan 05, 2010 |
Objections/Comments Received |
Jan 06, 2010 |
Objections/Comments Received |
Jan 08, 2010 |
Objection withdrawal received |
Jan 08, 2010 |
Public Notice End Date |
Jan 12, 2010 |
Additional Information Received |
Jan 12, 2010 |
Objections/Comments Received |
Jan 13, 2010 |
Additional Information Received |
Feb 08, 2010 |
Correspondence Received |
Feb 08, 2010 |
Objections/Comments Received |
Feb 08, 2010 |
Public Notice End Date Extension Granted |
Feb 08, 2010 |
Correspondence Received |
Feb 09, 2010 |
Entry of Appearance Received |
Feb 09, 2010 |
Objections/Comments Received |
Feb 10, 2010 |
Correspondence Received |
Feb 12, 2010 |
HPHC Historical Preservation No Effect |
Aug 20, 2010 |
Correspondence Received |
Aug 23, 2010 |
Additional Information Received |
Aug 24, 2010 |
Additional Information Received |
Aug 24, 2010 |
Additional Information Received |
Aug 25, 2010 |
30 day Public Notice Issued |
Sep 23, 2010 |
Objections/Comments Received |
Sep 25, 2010 |
Public Notice End Date |
Sep 27, 2010 |
Correspondence Received |
Oct 04, 2010 |
Water Quality Certification |
Oct 04, 2010 |
Water Quality Certification |
Oct 05, 2010 |
Objections/Comments Received |
Oct 21, 2010 |
Objections/Comments Received |
Nov 03, 2010 |
Plans Received |
Nov 04, 2010 |
Executive Signoff of Staff Reports |
Nov 04, 2010 |
Biologist Report |
Nov 04, 2010 |
Engineering Report |
Nov 18, 2010 |
Ready to Schedule Semi-Monthly Meeting |
Nov 18, 2010 |
Special Exception Public Hearing Notice mailed |
Nov 29, 2010 |
US Army Corp of Engineers Permit Date |
Dec 01, 2010 |
Correspondence Received |
Dec 14, 2010 |
Council Approval Granted |
Dec 14, 2010 |
Semi-Monthly Meeting Held |
Dec 14, 2010 |
Semi-Monthly Meeting Date Scheduled |
Dec 17, 2010 |
HPHC Historical Preservation No Effect |
Dec 21, 2010 |
Stipulation Package from Biologist |
Dec 21, 2010 |
Stipulation Package by Engineer |
Dec 22, 2010 |
Typist for Processing |
Dec 22, 2010 |
Permit Approved |
Jan 13, 2011 |
RIDEM Approval required |
Feb 07, 2011 |
30 Day Appeal Notification to Owner |
Feb 07, 2011 |
Legal Response/Decision |
Feb 11, 2011 |
Executive Sign Off |
Feb 11, 2011 |
Sent to Photo Copy |
Feb 15, 2011 |
Land Evidence Date |
Sep 26, 2011 |
Additional Information Received |
Jan 19, 2012 |
Letter of Authorization |
Mar 02, 2012 |
Letter of Authorization |
May 29, 2012 |
Additional Information Received |
Jul 18, 2012 |
Modification Request |
Jul 26, 2012 |
Biologist Report |
Jul 26, 2012 |
Engineering Report |
Jul 26, 2012 |
Typist for Processing |
Jul 26, 2012 |
Executive Sign Off |
Jul 26, 2012 |
Sent to Photo Copy |
Jul 26, 2012 |
Modification Approved |
Jul 31, 2012 |
Land Evidence Date |
Aug 27, 2012 |
HPHC Historical Preservation No Effect |
Sep 01, 2012 |
HPHC Historical Preservation No Effect |
Oct 01, 2012 |
Note to File |