Action Date | Action Description |
---|---|
Feb 22, 2010 | Assent Application Received |
Feb 22, 2010 | Administrative Review for Completeness |
Feb 23, 2010 | Team Review for Completeness |
Feb 23, 2010 | Application Accepted |
Mar 03, 2010 | 30 day Public Notice Issued |
Mar 04, 2010 | HPHC Historical Preservation No Effect |
Apr 03, 2010 | Public Notice End Date |
Apr 05, 2010 | Dock Meeting -- Approval |
Apr 05, 2010 | Category A* (Docks) |
Apr 13, 2010 | Biologist Report |
Apr 14, 2010 | Typist for Processing |
Apr 14, 2010 | Executive Sign Off |
Apr 14, 2010 | Sent to Photo Copy |
Apr 14, 2010 | Permit Approved |
Apr 16, 2010 | US Army Corp of Engineers Permit Date |
Apr 21, 2010 | US Army Corps of Engineers Approval Received |
May 14, 2010 | Land Evidence Date |
Aug 09, 2016 | Expiration of Assent/End of Tolling Legislation |
Jul 06, 2017 | Modification Request |
Jul 10, 2017 | Administrative Review for Completeness |
Jul 10, 2017 | Team Review for Completeness |
Jul 10, 2017 | Application Accepted |
Jul 13, 2017 | Additional Information Received |
Jul 19, 2017 | HPHC Historical Preservation No Effect |
Aug 01, 2017 | Commencement of Work Notice received |
Aug 08, 2017 | Typist for Processing |
Aug 08, 2017 | Executive Sign Off |
Aug 08, 2017 | Sent to Photo Copy |
Aug 08, 2017 | Modification Approved |
Aug 08, 2017 | Biologist Report |
Aug 28, 2017 | Land Evidence Date |