Action Date | Action Description |
---|---|
Apr 15, 2010 | Assent Application Received |
Apr 16, 2010 | Administrative Review for Completeness |
Apr 16, 2010 | Team Review for Completeness |
Apr 16, 2010 | Team Review for Completeness |
Apr 16, 2010 | Application Accepted |
May 20, 2010 | HPHC Historical Preservation No Effect |
Aug 27, 2010 | Additional Information Received |
Sep 15, 2010 | HPHC Historical Preservation No Effect |
Sep 16, 2010 | Typist for Processing |
Sep 16, 2010 | Biologist Report |
Sep 20, 2010 | Engineering Report |
Sep 20, 2010 | Executive Sign Off |
Sep 20, 2010 | Sent to Photo Copy |
Sep 27, 2010 | Land Evidence Date |
Oct 28, 2010 | Water Quality Certification |
Nov 22, 2010 | Commencement of Work Notice received |
Jan 19, 2011 | Monitoring Report |